A space-constrained resource-constrained scheduling system for multi-story buildings

Abstract

dc:description.abstract

Current planning and scheduling techniques ignore the requirements of activities for work area or space. Any task or activity requires a specific work space for its execution. This demand is based on the space requirements of each resource allocated to the activity. When such required demand becomes unavailable, the activity or task can not be executed or, in some cases, is performed with a lower productivity rate. This is because performance and maneuvering of either crew or equipment may become difficult and sometimes not possible. This research provides a structured methodology to deal with the problem of limited work space availability. The research’s domain focuses on multi-story building construction with particular focus on the repetitive portion of the facility (i.e. typical floors). The research studies the issues of work space as a new decision factor for schedule generation in this type of construction. A scheduling model is developed to define and incorporate work space availability in the scheduling process. The model includes a method to quantify work space parameters (space demand and space availability) for any activity. The model also presents a procedure to compare space demand to availability and provide scheduling decisions to Sequence each activity based on these two parameters. The model allows for availability limits to be placed on resources required for the work by implementing limited resource scheduling techniques in the scheduling procedures. Horizontal and vertical logic constraints associated with repetitive work are also incorporated in the scheduling process of the model. Work continuity issues and varying productivity rates are used as scheduling decision options. The model adopts a procedure to schedule non-continuous activities using variable length segments along the typical floors. In addition, the model allows for adjusting the initial defined resource demand pools for different activities to account for any modifications that may occur to the activity duration during scheduling. Loss of productivity as a result of the combined effect of travel time and learning curve phenomena is also incorporated in the generation of the schedule by the model. The model is taken to a prototype proof of concept by developing SCaRC (Space Constrained and Resource Constrained) scheduling system. The system is implemented using a knowledge-based approach.

Degree

thesis:*
Name thesis:degree_name
Ph. D.
Level thesis:degree_level
doctoral
Discipline thesis:degree_discipline
Civil Engineering
Department dc:contributor.department
Civil Engineering
Grantor dc:publisher
Virginia Tech
Year dc:date.issued
1992

Author and committee

dc:creator, dc:contributor.*
Author dc:creator
  • Thabet, Walid
Chair dc:contributor.committeechair
  • Beliveau, Yvan
Committee members dc:contributor.committeemember
  • Vorster, Michael
  • de la Garza, Jesus M.
  • Rakes, Terry R.
  • Jayaram, S.

Rights

dc:rights
Statement dc:rights
  • In Copyright
Language dc:language.iso
en

Identifiers

dc:identifier.*
Dc Identifier Other
etd-02022007-133635
OAI identifier oai:identifier
oai:vtechworks.lib.vt.edu:10919/37272

Chain of custody

source
Harvested from
Virginia Tech
Base URL
vtechworks.lib.vt.edu/oai/request
Last updated
2026-07-22
Source record
OAI-PMH GetRecord
related terms
citation

Thabet, Walid. A space-constrained resource-constrained scheduling system for multi-story buildings. doctoral thesis, Virginia Tech, 1992. http://hdl.handle.net/10919/37272