Relationship between procurement duration and project performance in design-build water/wastewater projects

Abstract

dc:description.abstract

The design-build (DB) project delivery system (PDS) has been widely applied and studied in the construction industry. Its advantages include shortened project duration, lowered risk to the owner, improved project performance, and possibly reduced cost. Researchers have also studied the factors related to the improved performance in DB projects, especially in the building and transportation industries. Compared to the building and highway industries, the application of DB in water/wastewater (WW) projects has been rarely studied before. One of the potential factors that may influence project performance is procurement duration (PD). By focusing on DB applied to WW projects, this study explored the relationship between PD (from Request for Proposal issue date to proposal due date) and project success. The project success criteria was defined as cost and schedule growth, which were objective measurements and thus provided more convincing data analysis. Project data was collected through an on-line questionnaire given to owners and design-builders who had experience in DB WW projects. The data was used to analyze how PD impacts project performance in terms of cost and schedule growth. The relationships between PD and performance in DB WW projects were compared to DB transportation projects. Both similarities and differences were found. To explore the reasons of these similarities and differences, content analysis was conducted to compare the DB WW and transportation procurement documents. Variables were defined and analyzed based on their frequency of use within procurement documents. Hypotheses were given based on the similarities and differences found between DB WW and transportation projects procurement items as to which might influence the project success. Related suggestions were provided for owners in the DB WW industry regarding the time given for design-builders to prepare proposals and items that should be required in the DB proposal.'

Degree

thesis:*
Name thesis:degree_name
Civil Engineering
Level thesis:degree_level
Thesis
Discipline thesis:degree_discipline
Civil Engineering
Year
2010

Author and committee

dc:creator, dc:contributor.*
Author dc:creator
  • Jin, Ruoyu
Contributors dc:contributor
  • Bogus, Susan
  • Migliaccio, Giovanni
  • Schuler, Andrew

Subjects

dc:subject × 4

Rights

Language dc:language
English

Identifiers

dc:identifier.*
OAI identifier oai:identifier
oai:digitalrepository.unm.edu:ce_etds-1115

Chain of custody

source
Harvested from
University of New Mexico
Base URL
digitalrepository.unm.edu/do/oai/
Last updated
2026-07-24
Source record
OAI-PMH GetRecord
citation

Jin, Ruoyu. Relationship between procurement duration and project performance in design-build water/wastewater projects. Thesis thesis, 2010. http://hdl.handle.net/1928/10828