DESIGN FOR ASSEMBLY AND SCHEDULE OPTIMIZATION FOR LARGE STRUCTURE CONSTRUCTION

Abstract

dc:description.abstract

The efficient construction or assembly of a large structure is a critical factor in the success of a project because of the cost and time required. The construction of a large structure is long and expensive due to the number of processes and resources required, the complexity of the processes and the dependencies between tasks. Two methods have been identified for increasing construction efficiency: Design for Assembly (DFA) and schedule optimization. To improve assembly efficiency of smaller products, DFA methodologies have been widely developed and applied. The basis of these methods is to reduce the number of parts in the assembly and to provide a quantitative measure of the assembly efficiency. To achieve similar advantages to those DFA has provided for smaller assemblies, design for large assembly guidelines have been developed. The guidelines are the result of identifying relevant paradigms and the considerations which affect assembly efficiency. The paradigms which have been identified are concurrent engineering, simplicity and modularity. The considerations which must be addressed to improve assembly are joining, handling, 'positioning and assembly planning. To aid designers, the paradigms and considerations have been formulated as guidelines and organized to correspond with the design process. Resource constrained project scheduling is an active area of research focused on reducing project duration and cost. Several optimization techniques have been investigated, including heuristics, branch and bound, genetic algorithms and constraint satisfaction. A new algorithm for resource constrained schedule project optimization has been developed which combines genetic algorithms and constraint satisfaction. The algorithm uses a genetic algorithm to determine the priority of the tasks for resource allocation. Constraint satisfaction techniques are used to generate the schedules. The algorithm has been implemented in a computer program and demonstrated by successfully solving two problems taken from literature.

Degree

thesis:*
Name thesis:degree_name
Master of Science (M.Sc.)
Level thesis:degree_level
Masters
Discipline thesis:degree_discipline
Mechanical Engineering
Grantor
University of Saskatchewan
Year dc:date.issued
1999

Author and committee

dc:creator, dc:contributor.*
Author dc:creator
  • Sauder, Harold Paul
Advisor dc:contributor.advisor
  • Gu, Peihua

Identifiers

dc:identifier.*
Handle dc:identifier.uri
https://hdl.handle.net/10388/7980
OAI identifier oai:identifier
oai:harvest.usask.ca:10388/7980

Chain of custody

source
Harvested from
University of Saskatchewan
Base URL
harvest.usask.ca/server/oai/request
Last updated
2026-07-24
Source record
OAI-PMH GetRecord
related terms
citation

Sauder, Harold Paul. DESIGN FOR ASSEMBLY AND SCHEDULE OPTIMIZATION FOR LARGE STRUCTURE CONSTRUCTION. Masters thesis, University of Saskatchewan, 1999. https://hdl.handle.net/10388/7980