Materials lead time reduction in a semiconductor equipment manufacturing plant : warehouse design and layout

Abstract

dc:description.abstract

The warehouse layout and operations of a semiconductor tool manufacturer were studied with the objective of reducing the lead time for parts ordered from the warehouse to 8 hours. Current order fulfillment operations were studied and interviews with involved personnel were conducted. Additionally, data was extracted and analyzed from the company's SAP Extended Warehouse Management database to analyze the past performance of the warehouse operations. Three main areas for improvements were analyzed and recommendations were made regarding each area. First, it is recommended that a kit of parts ordered should be sent immediately the constituent parts are consolidated and the kit is completed. This saves an average of 6 hours that parts in a complete kit wait for other kits to be completed before being sent out. Second, the picking aisles of the warehouse should be cleared so that parts in storage locations are easily accessed for picking and no time is wasted on clearing a path to pick a part. This leads to an average time saving of 1.2 hours per day on the time parts are delivered. Third, the receiving and sorting areas in the warehouse should be combined together. This frees up storage space for excess bulk material which block picking aisles. These recommendations are to be combined with other material flow improvements. It was determined that the goal of 8 hours lead time is unrealistic. However, calculations suggest that lead time will be reduced to 16 hours.

Degree

thesis:*
Department dc:contributor.department
Massachusetts Institute of Technology. Department of Mechanical Engineering.
Grantor dc:publisher
Massachusetts Institute of Technology
Year dc:date.issued
2013

Author and committee

dc:creator, dc:contributor.*
Author dc:creator
  • Ukpebor, Obehi
Advisor dc:contributor.advisor
  • Stephen C. Graves.

Subjects

dc:subject × 1

Rights

dc:rights
Statement dc:rights
  • M.I.T. theses are protected by copyright. They may be viewed from this source for any purpose, but reproduction or distribution in any format is prohibited without written permission. See provided URL for inquiries about permission.
Language dc:language.iso
eng

Identifiers

dc:identifier.*
Handle dc:identifier.uri
http://hdl.handle.net/1721.1/85784
OAI identifier oai:identifier
oai:dspace.mit.edu:1721.1/85784

Chain of custody

source
Harvested from
MIT
Base URL
dspace.mit.edu/oai/request
Last updated
2026-07-22
Source record
OAI-PMH GetRecord
citation

Ukpebor, Obehi. Materials lead time reduction in a semiconductor equipment manufacturing plant : warehouse design and layout. Massachusetts Institute of Technology, 2013. http://hdl.handle.net/1721.1/85784