{"id":{"repo_id":"mit","oai_identifier":"oai:dspace.mit.edu:1721.1/70276"},"canonical_url":"https://search.dev.ndltd.org/etd/mit/oai:dspace.mit.edu:1721.1/70276","repository":{"repo_id":"mit","name":"MIT","base_url":"https://dspace.mit.edu/oai/request"},"display":{"title":"Application of life cycle costing method to a renovation project","abstract":"In this study, we have examined the application of Lee analysis method to the construction and renovation stages of a building project. The application of the Lee analysis is currently limited to the very early stages of a project life, namely at the concept and design stages. We propose application of the Lee method, with several modifications, to the construction and renovation stages. The simplified Lee method is proposed and examined in the first two case studies. The simplified method limits the range and complexity of data inputs, and is intended to be an Lee used by engineers practicing in the construction industry. In the third case study, the \"Lee per square-foot\", which implements the concept of the \"square-foot\" cost estimating, is proposed. This method is intended to be used to assess the residual value and to estimate running costs of an existing building. Necessary modifications of the Lee, as well as the accuracy and limits of these new methods are examined through three case studies.","abstract_html":"In this study, we have examined the application of Lee analysis method to the construction and renovation stages of a building project. The application of the Lee analysis is currently limited to the very early stages of a project life, namely at the concept and design stages. We propose application of the Lee method, with several modifications, to the construction and renovation stages. The simplified Lee method is proposed and examined in the first two case studies. The simplified method limits the range and complexity of data inputs, and is intended to be an Lee used by engineers practicing in the construction industry. In the third case study, the &quot;Lee per square-foot&quot;, which implements the concept of the &quot;square-foot&quot; cost estimating, is proposed. This method is intended to be used to assess the residual value and to estimate running costs of an existing building. Necessary modifications of the Lee, as well as the accuracy and limits of these new methods are examined through three case studies.","abstract_has_math":false,"creators":["Taneda, Makoto"],"institution":"Massachusetts Institute of Technology","degree_name":null,"degree_level":null,"degree_discipline":null,"degree_department":"Massachusetts Institute of Technology. Dept. of Architecture.","school":null,"contributors":[],"advisors":["Leonard J. Morse-Fortier."],"committee_chairs":[],"committee_members":[],"year":1996,"date_issued":"1996","date_published":"1996","updated_at":"2026-07-22T22:22:06Z","subjects":["Architecture."],"languages":["eng"],"rights":["M.I.T. theses are protected by copyright. They may be viewed from this source for any purpose, but reproduction or distribution in any format is prohibited without written permission. See provided URL for inquiries about permission."],"rights_urls":["http://dspace.mit.edu/handle/1721.1/7582"],"identifier_entries":[]},"links":{"outbound_url":"http://hdl.handle.net/1721.1/70276","outbound_label":"Handle","outbound_source":"dc:identifier.uri"},"metadata_groups":[{"id":"people","label":"People","entries":[{"key":"dc:contributor.advisor","label":"Advisor","values":["Leonard J. Morse-Fortier."]},{"key":"dc:contributor.department","label":"Department","values":["Massachusetts Institute of Technology. Dept. of Architecture."]},{"key":"dc:contributor.other","label":"Dc Contributor Other","values":["Massachusetts Institute of Technology. Dept. of Architecture."]},{"key":"dc:creator","label":"Author","values":["Taneda, Makoto"]}]},{"id":"academic_context","label":"Academic Context","entries":[{"key":"dc:date.accessioned","label":"Dc Date Accessioned","values":["2012-04-26T18:34:43Z"]},{"key":"dc:date.available","label":"Dc Date Available","values":["2012-04-26T18:34:43Z"]},{"key":"dc:date.issued","label":"Date","values":["1996"]},{"key":"dc:publisher","label":"Institution","values":["Massachusetts Institute of Technology"]},{"key":"dc:type","label":"Dc Type","values":["Thesis"]}]},{"id":"subjects_keywords","label":"Subjects and Keywords","entries":[{"key":"dc:subject","label":"Dc Subject","values":["Architecture."]}]},{"id":"language_rights","label":"Language and Rights","entries":[{"key":"dc:language.iso","label":"Language (ISO)","values":["eng"]},{"key":"dc:rights","label":"Dc Rights","values":["M.I.T. theses are protected by copyright. They may be viewed from this source for any purpose, but reproduction or distribution in any format is prohibited without written permission. See provided URL for inquiries about permission."]},{"key":"dc:rights.uri","label":"Rights URI","values":["http://dspace.mit.edu/handle/1721.1/7582"]}]},{"id":"identifiers","label":"Identifiers","entries":[{"key":"dc:identifier.uri","label":"Identifier URI","values":["http://hdl.handle.net/1721.1/70276"]}]},{"id":"additional","label":"Additional Metadata","entries":[{"key":"dc:description","label":"Description","values":["Thesis (M.S.)--Massachusetts Institute of Technology, Dept. of Architecture, 1996.","Includes bibliographical references (leaves 115-116)."]},{"key":"dc:description.abstract","label":"Abstract","values":["In this study, we have examined the application of Lee analysis method to the construction and renovation stages of a building project. The application of the Lee analysis is currently limited to the very early stages of a project life, namely at the concept and design stages. We propose application of the Lee method, with several modifications, to the construction and renovation stages. The simplified Lee method is proposed and examined in the first two case studies. The simplified method limits the range and complexity of data inputs, and is intended to be an Lee used by engineers practicing in the construction industry. In the third case study, the \"Lee per square-foot\", which implements the concept of the \"square-foot\" cost estimating, is proposed. This method is intended to be used to assess the residual value and to estimate running costs of an existing building. Necessary modifications of the Lee, as well as the accuracy and limits of these new methods are examined through three case studies."]},{"key":"dc:description.degree","label":"Dc Description Degree","values":["M.S."]},{"key":"dc:title","label":"Title","values":["Application of life cycle costing method to a renovation project"]}]}],"canonical_facts":{"dc:contributor.advisor":["Leonard J. Morse-Fortier."],"dc:contributor.department":["Massachusetts Institute of Technology. Dept. of Architecture."],"dc:contributor.other":["Massachusetts Institute of Technology. Dept. of Architecture."],"dc:creator":["Taneda, Makoto"],"dc:date.accessioned":["2012-04-26T18:34:43Z"],"dc:date.available":["2012-04-26T18:34:43Z"],"dc:date.issued":["1996"],"dc:description":["Thesis (M.S.)--Massachusetts Institute of Technology, Dept. of Architecture, 1996.","Includes bibliographical references (leaves 115-116)."],"dc:description.abstract":["In this study, we have examined the application of Lee analysis method to the construction and renovation stages of a building project. The application of the Lee analysis is currently limited to the very early stages of a project life, namely at the concept and design stages. We propose application of the Lee method, with several modifications, to the construction and renovation stages. The simplified Lee method is proposed and examined in the first two case studies. The simplified method limits the range and complexity of data inputs, and is intended to be an Lee used by engineers practicing in the construction industry. In the third case study, the \"Lee per square-foot\", which implements the concept of the \"square-foot\" cost estimating, is proposed. This method is intended to be used to assess the residual value and to estimate running costs of an existing building. Necessary modifications of the Lee, as well as the accuracy and limits of these new methods are examined through three case studies."],"dc:description.degree":["M.S."],"dc:identifier.uri":["http://hdl.handle.net/1721.1/70276"],"dc:language.iso":["eng"],"dc:publisher":["Massachusetts Institute of Technology"],"dc:rights":["M.I.T. theses are protected by copyright. They may be viewed from this source for any purpose, but reproduction or distribution in any format is prohibited without written permission. See provided URL for inquiries about permission."],"dc:rights.uri":["http://dspace.mit.edu/handle/1721.1/7582"],"dc:subject":["Architecture."],"dc:title":["Application of life cycle costing method to a renovation project"],"dc:type":["Thesis"]},"updated_at":"2026-07-22T22:22:06Z"}