Using critical chain project management methodologies to build a production schedule

Abstract

dc:description.abstract

Critical Chain project management methodologies have been used for the last ten years to manage a wide range of projects. These methods, which apply Eli Goldratt's Theory of Constraints, have demonstrated the ability to complete projects faster and with greater predictability. While the focus of Critical Chain has been on projects of a finite duration, such as product development efforts, the application of these techniques in a more continuous, manufacturing setting can also bring about the same benefits of decreased time and increased predictability. In a customized product environment, where each product is a unique project, scheduling production requires more than the creation of a schedule and the management of manufacturing resources. Information must be created and managed from the moment a project is initiated through its implementation. It is the proper management of the essential project details across functions: materials, labor activities, and their timing, that enables faster project lead times and lower overall costs. ABB Raffin Electric's labor and material costs were 15% higher than expected for 2008 due to cost and schedule slippage. This thesis shows how a process for managing project information could have recovered 75% of the lost costs through the proper management of materials and labor activities. Costs and activity durations were estimated using a tool that combined small, common groups of materials and labor activities into complex assemblies.

Degree

thesis:*
Department dc:contributor.department
Leaders for Manufacturing Program at MIT
Grantor dc:publisher
Massachusetts Institute of Technology
Year dc:date.issued
2009

Author and committee

dc:creator, dc:contributor.*
Author dc:creator
  • Poppe, Clayton D. (Clayton Douglas)
Advisor dc:contributor.advisor
  • Stephen C. Graves and Oliver [i.e. Olivier] de Weck.

Subjects

dc:subject × 3

Rights

dc:rights
Statement dc:rights
  • M.I.T. theses are protected by copyright. They may be viewed from this source for any purpose, but reproduction or distribution in any format is prohibited without written permission. See provided URL for inquiries about permission.
Language dc:language.iso
eng

Identifiers

dc:identifier.*
Handle dc:identifier.uri
http://hdl.handle.net/1721.1/49785
OAI identifier oai:identifier
oai:dspace.mit.edu:1721.1/49785

Chain of custody

source
Harvested from
MIT
Base URL
dspace.mit.edu/oai/request
Last updated
2026-07-22
Source record
OAI-PMH GetRecord
citation

Poppe, Clayton D. (Clayton Douglas). Using critical chain project management methodologies to build a production schedule. Massachusetts Institute of Technology, 2009. http://hdl.handle.net/1721.1/49785