{"id":{"repo_id":"mit","oai_identifier":"oai:dspace.mit.edu:1721.1/30134"},"canonical_url":"https://search.dev.ndltd.org/etd/mit/oai:dspace.mit.edu:1721.1/30134","repository":{"repo_id":"mit","name":"MIT","base_url":"https://dspace.mit.edu/oai/request"},"display":{"title":"Schedule and cost estimate for an innovative Boston Harbor concert hall","abstract":"This thesis formulates a cost estimate and schedule for constructing the Boston Concert Hall, an innovative hypothetical building composed of two concert halls and a restaurant. Concert Halls are complex and expensive structures due to steep design requirements reflecting their status as signature buildings and because they require extensive furnishing. Restaurants are not as complex but require the same kind of attention in their interior furnishing as well as in the choice of their kitchen equipment. Because the structure houses two complicated entities, feasibility analysis required a careful cost and schedule estimation. On the basis of several assumptions, a rough estimate of the cost and schedule of the entire structure has been developed along with a more detailed estimate of the two auditoriums and the restaurant. The study suggests that the interior finishing of such unique buildings represent a large fraction of their overall costs and construction time.","abstract_html":"This thesis formulates a cost estimate and schedule for constructing the Boston Concert Hall, an innovative hypothetical building composed of two concert halls and a restaurant. Concert Halls are complex and expensive structures due to steep design requirements reflecting their status as signature buildings and because they require extensive furnishing. Restaurants are not as complex but require the same kind of attention in their interior furnishing as well as in the choice of their kitchen equipment. Because the structure houses two complicated entities, feasibility analysis required a careful cost and schedule estimation. On the basis of several assumptions, a rough estimate of the cost and schedule of the entire structure has been developed along with a more detailed estimate of the two auditoriums and the restaurant. The study suggests that the interior finishing of such unique buildings represent a large fraction of their overall costs and construction time.","abstract_has_math":false,"creators":["Coste, Amelie, 1982-"],"institution":"Massachusetts Institute of Technology","degree_name":null,"degree_level":null,"degree_discipline":null,"degree_department":"Massachusetts Institute of Technology. Dept. of Civil and Environmental Engineering.","school":null,"contributors":[],"advisors":["Jerome J. Connor and Nathaniel Osgood."],"committee_chairs":[],"committee_members":[],"year":2004,"date_issued":"2004","date_published":"2004","updated_at":"2026-07-22T22:22:23Z","subjects":["Civil and Environmental Engineering."],"languages":["eng"],"rights":["M.I.T. theses are protected by copyright. They may be viewed from this source for any purpose, but reproduction or distribution in any format is prohibited without written permission. See provided URL for inquiries about permission."],"rights_urls":["http://dspace.mit.edu/handle/1721.1/7582"],"identifier_entries":[]},"links":{"outbound_url":"http://hdl.handle.net/1721.1/30134","outbound_label":"Handle","outbound_source":"dc:identifier.uri"},"metadata_groups":[{"id":"people","label":"People","entries":[{"key":"dc:contributor.advisor","label":"Advisor","values":["Jerome J. Connor and Nathaniel Osgood."]},{"key":"dc:contributor.department","label":"Department","values":["Massachusetts Institute of Technology. Dept. of Civil and Environmental Engineering."]},{"key":"dc:contributor.other","label":"Dc Contributor Other","values":["Massachusetts Institute of Technology. Dept. of Civil and Environmental Engineering."]},{"key":"dc:creator","label":"Author","values":["Coste, Amelie, 1982-"]}]},{"id":"academic_context","label":"Academic Context","entries":[{"key":"dc:date.accessioned","label":"Dc Date Accessioned","values":["2006-03-24T18:22:43Z"]},{"key":"dc:date.available","label":"Dc Date Available","values":["2006-03-24T18:22:43Z"]},{"key":"dc:date.issued","label":"Date","values":["2004"]},{"key":"dc:publisher","label":"Institution","values":["Massachusetts Institute of Technology"]},{"key":"dc:type","label":"Dc Type","values":["Thesis"]}]},{"id":"subjects_keywords","label":"Subjects and Keywords","entries":[{"key":"dc:subject","label":"Dc Subject","values":["Civil and Environmental Engineering."]}]},{"id":"language_rights","label":"Language and Rights","entries":[{"key":"dc:language.iso","label":"Language (ISO)","values":["eng"]},{"key":"dc:rights","label":"Dc Rights","values":["M.I.T. theses are protected by copyright. They may be viewed from this source for any purpose, but reproduction or distribution in any format is prohibited without written permission. See provided URL for inquiries about permission."]},{"key":"dc:rights.uri","label":"Rights URI","values":["http://dspace.mit.edu/handle/1721.1/7582"]}]},{"id":"identifiers","label":"Identifiers","entries":[{"key":"dc:identifier.uri","label":"Identifier URI","values":["http://hdl.handle.net/1721.1/30134"]}]},{"id":"additional","label":"Additional Metadata","entries":[{"key":"dc:description","label":"Description","values":["Thesis (M. Eng.)--Massachusetts Institute of Technology, Dept. of Civil and Environmental Engineering, 2004.","Includes bibliographical references (leaves 75-77)."]},{"key":"dc:description.abstract","label":"Abstract","values":["This thesis formulates a cost estimate and schedule for constructing the Boston Concert Hall, an innovative hypothetical building composed of two concert halls and a restaurant. Concert Halls are complex and expensive structures due to steep design requirements reflecting their status as signature buildings and because they require extensive furnishing. Restaurants are not as complex but require the same kind of attention in their interior furnishing as well as in the choice of their kitchen equipment. Because the structure houses two complicated entities, feasibility analysis required a careful cost and schedule estimation. On the basis of several assumptions, a rough estimate of the cost and schedule of the entire structure has been developed along with a more detailed estimate of the two auditoriums and the restaurant. The study suggests that the interior finishing of such unique buildings represent a large fraction of their overall costs and construction time."]},{"key":"dc:description.degree","label":"Dc Description Degree","values":["M.Eng."]},{"key":"dc:format.mimetype","label":"Dc Format Mimetype","values":["application/pdf"]},{"key":"dc:title","label":"Title","values":["Schedule and cost estimate for an innovative Boston Harbor concert hall"]}]}],"canonical_facts":{"dc:contributor.advisor":["Jerome J. Connor and Nathaniel Osgood."],"dc:contributor.department":["Massachusetts Institute of Technology. Dept. of Civil and Environmental Engineering."],"dc:contributor.other":["Massachusetts Institute of Technology. Dept. of Civil and Environmental Engineering."],"dc:creator":["Coste, Amelie, 1982-"],"dc:date.accessioned":["2006-03-24T18:22:43Z"],"dc:date.available":["2006-03-24T18:22:43Z"],"dc:date.issued":["2004"],"dc:description":["Thesis (M. Eng.)--Massachusetts Institute of Technology, Dept. of Civil and Environmental Engineering, 2004.","Includes bibliographical references (leaves 75-77)."],"dc:description.abstract":["This thesis formulates a cost estimate and schedule for constructing the Boston Concert Hall, an innovative hypothetical building composed of two concert halls and a restaurant. Concert Halls are complex and expensive structures due to steep design requirements reflecting their status as signature buildings and because they require extensive furnishing. Restaurants are not as complex but require the same kind of attention in their interior furnishing as well as in the choice of their kitchen equipment. Because the structure houses two complicated entities, feasibility analysis required a careful cost and schedule estimation. On the basis of several assumptions, a rough estimate of the cost and schedule of the entire structure has been developed along with a more detailed estimate of the two auditoriums and the restaurant. The study suggests that the interior finishing of such unique buildings represent a large fraction of their overall costs and construction time."],"dc:description.degree":["M.Eng."],"dc:format.mimetype":["application/pdf"],"dc:identifier.uri":["http://hdl.handle.net/1721.1/30134"],"dc:language.iso":["eng"],"dc:publisher":["Massachusetts Institute of Technology"],"dc:rights":["M.I.T. theses are protected by copyright. They may be viewed from this source for any purpose, but reproduction or distribution in any format is prohibited without written permission. See provided URL for inquiries about permission."],"dc:rights.uri":["http://dspace.mit.edu/handle/1721.1/7582"],"dc:subject":["Civil and Environmental Engineering."],"dc:title":["Schedule and cost estimate for an innovative Boston Harbor concert hall"],"dc:type":["Thesis"]},"updated_at":"2026-07-22T22:22:23Z"}