Improved methods for managing megaprojects

Abstract

dc:description.abstract

Nuclear power is in danger of fading away as a signicant source of energy supply in some parts of the world unless it becomes more competitive. The cost of nuclear energy largely depends on capital cost because nuclear power plants are very expensive to design and build and relatively cheap to operate. The capital cost of nuclear power plants is literally dominated by factors other than those of physical equipment, such as project preparation, site preparation, engineering, planning, installation, and management. Interestingly, project planning, monitoring, execution and management is where too often the nuclear industry has failed in the past. As of 2014, the average time and cost overrun for nuclear projects worldwide are 64% and 117.3%, respectively. There is evidence showing that there is something that we fundamentally do not understand (or represent) in project planning and management. This work is based on the premise that nuclear projects are megaprojects.

Degree

thesis:*
Name thesis:degree_name
Doctoral
Department dc:contributor.department
Massachusetts Institute of Technology. Department of Nuclear Science and Engineering
Grantor dc:publisher
Massachusetts Institute of Technology
Year dc:date.issued
2020

Author and committee

dc:creator, dc:contributor.*
Author dc:creator
  • Minelli, Paolo,Ph. D.Massachusetts Institute of Technology.
Advisor dc:contributor.advisor
  • Michael W. Golay.

Subjects

dc:subject × 1

Rights

dc:rights
Statement dc:rights
  • MIT theses may be protected by copyright. Please reuse MIT thesis content according to the MIT Libraries Permissions Policy, which is available through the URL provided.
Language dc:language.iso
eng

Identifiers

dc:identifier.*
Handle dc:identifier.uri
https://hdl.handle.net/1721.1/129920
OAI identifier oai:identifier
oai:dspace.mit.edu:1721.1/129920

Chain of custody

source
Harvested from
MIT
Base URL
dspace.mit.edu/oai/request
Last updated
2026-07-22
Source record
OAI-PMH GetRecord
citation

Minelli, Paolo,Ph. D.Massachusetts Institute of Technology.. Improved methods for managing megaprojects. Massachusetts Institute of Technology, 2020. https://hdl.handle.net/1721.1/129920