{"id":{"repo_id":"bradford","oai_identifier":"oai:bradscholars.brad.ac.uk:10454/4399"},"canonical_url":"https://search.dev.ndltd.org/etd/bradford/oai:bradscholars.brad.ac.uk:10454/4399","repository":{"repo_id":"bradford","name":"University of Bradford","base_url":"https://bradscholars.brad.ac.uk/oai/request"},"display":{"title":"Control of construction contracts. Analysis of systems for the control of progress, quality and cost of construction to the client, based upon six cases in building or civil engineering in the UK.","abstract":"Six civil engineering and building projects under construction have been observed in order to compare theory and practice, and thus draw conclusions on how Clients and their management teams may control construction effectively. It has been reported and the six studies have shown that during construction as problems occur decisions taken to tackle them result in changes to one or more of the independant variables cost, time and performance. It is therefore argued in this thesis that if these variables are to be controlled to Xhe. Client's benefit:. - clear responsibilities, duties and authority to make decisions should be given to the members of project management teams. -a project control system should be set up which will help the management team to perform those duties. - both the management team and the system should be organized to suit the particular project and Client.","abstract_html":"Six civil engineering and building projects under construction have been observed in order to compare theory and practice, and thus draw conclusions on how Clients and their management teams may control construction effectively. It has been reported and the six studies have shown that during construction as problems occur decisions taken to tackle them result in changes to one or more of the independant variables cost, time and performance. It is therefore argued in this thesis that if these variables are to be controlled to Xhe. Client&#x27;s benefit:. - clear responsibilities, duties and authority to make decisions should be given to the members of project management teams. -a project control system should be set up which will help the management team to perform those duties. - both the management team and the system should be organized to suit the particular project and Client.","abstract_has_math":false,"creators":["Ninos, Gerassimos Emmanuel"],"institution":"University of Bradford","degree_name":null,"degree_level":null,"degree_discipline":null,"degree_department":null,"school":null,"contributors":[],"advisors":["Not named"],"committee_chairs":[],"committee_members":[],"year":2010,"date_issued":"2010-07-23T14:09:57Z","date_published":"2010-07-23T14:09:57Z","updated_at":"2026-07-24T01:14:20Z","subjects":["Construction contracts","Civil engineering projects","Building projects","Case studies","Project management","Decision making"],"languages":["en"],"rights":["<a rel=\"license\" href=\"http://creativecommons.org/licenses/by-nc-nd/3.0/\"><img alt=\"Creative Commons License\" style=\"border-width:0\" src=\"http://i.creativecommons.org/l/by-nc-nd/3.0/88x31.png\" /></a><br />The University of Bradford theses are licenced under a <a rel=\"license\" href=\"http://creativecommons.org/licenses/by-nc-nd/3.0/\">Creative Commons Licence</a>."],"rights_urls":[],"identifier_entries":[]},"links":{"outbound_url":"http://hdl.handle.net/10454/4399","outbound_label":"Handle","outbound_source":"dc:identifier.uri"},"metadata_groups":[{"id":"people","label":"People","entries":[{"key":"dc:contributor.advisor","label":"Advisor","values":["Not named"]},{"key":"dc:creator","label":"Author","values":["Ninos, Gerassimos Emmanuel"]}]},{"id":"academic_context","label":"Academic Context","entries":[{"key":"dc:date.accessioned","label":"Dc Date Accessioned","values":["2010-07-23T14:09:57Z"]},{"key":"dc:date.available","label":"Dc Date Available","values":["2010-07-23T14:09:57Z"]},{"key":"dc:date.issued","label":"Date","values":["2010-07-23T14:09:57Z"]},{"key":"dc:publisher.department","label":"Dc Publisher Department","values":["Postgraduate School of Studies in Technological Management"]},{"key":"dc:publisher.institution","label":"Dc Publisher Institution","values":["University of Bradford"]},{"key":"dc:type","label":"Dc Type","values":["Thesis"]},{"key":"dc:type.qualificationlevel","label":"Dc Type Qualificationlevel","values":["doctoral"]},{"key":"dc:type.qualificationname","label":"Dc Type Qualificationname","values":["PhD"]}]},{"id":"subjects_keywords","label":"Subjects and Keywords","entries":[{"key":"dc:subject","label":"Dc Subject","values":["Construction contracts","Civil engineering projects","Building projects","Case studies","Project management","Decision making"]}]},{"id":"language_rights","label":"Language and Rights","entries":[{"key":"dc:language.iso","label":"Language (ISO)","values":["en"]},{"key":"dc:rights","label":"Dc Rights","values":["<a rel=\"license\" href=\"http://creativecommons.org/licenses/by-nc-nd/3.0/\"><img alt=\"Creative Commons License\" style=\"border-width:0\" src=\"http://i.creativecommons.org/l/by-nc-nd/3.0/88x31.png\" /></a><br />The University of Bradford theses are licenced under a <a rel=\"license\" href=\"http://creativecommons.org/licenses/by-nc-nd/3.0/\">Creative Commons Licence</a>."]}]},{"id":"identifiers","label":"Identifiers","entries":[{"key":"dc:identifier.uri","label":"Identifier URI","values":["http://hdl.handle.net/10454/4399"]}]},{"id":"additional","label":"Additional Metadata","entries":[{"key":"dc:description.abstract","label":"Abstract","values":["Six civil engineering and building projects under construction have been observed in order to compare theory and practice, and thus draw conclusions on how Clients and their management teams may control construction effectively. It has been reported and the six studies have shown that during construction as problems occur decisions taken to tackle them result in changes to one or more of the independant variables cost, time and performance. It is therefore argued in this thesis that if these variables are to be controlled to Xhe. Client's benefit:. - clear responsibilities, duties and authority to make decisions should be given to the members of project management teams. -a project control system should be set up which will help the management team to perform those duties. - both the management team and the system should be organized to suit the particular project and Client."]},{"key":"dc:title","label":"Title","values":["Control of construction contracts. Analysis of systems for the control of progress, quality and cost of construction to the client, based upon six cases in building or civil engineering in the UK."]}]}],"canonical_facts":{"dc:contributor.advisor":["Not named"],"dc:creator":["Ninos, Gerassimos Emmanuel"],"dc:date.accessioned":["2010-07-23T14:09:57Z"],"dc:date.available":["2010-07-23T14:09:57Z"],"dc:date.issued":["2010-07-23T14:09:57Z"],"dc:description.abstract":["Six civil engineering and building projects under construction have been observed in order to compare theory and practice, and thus draw conclusions on how Clients and their management teams may control construction effectively. It has been reported and the six studies have shown that during construction as problems occur decisions taken to tackle them result in changes to one or more of the independant variables cost, time and performance. It is therefore argued in this thesis that if these variables are to be controlled to Xhe. Client's benefit:. - clear responsibilities, duties and authority to make decisions should be given to the members of project management teams. -a project control system should be set up which will help the management team to perform those duties. - both the management team and the system should be organized to suit the particular project and Client."],"dc:identifier.uri":["http://hdl.handle.net/10454/4399"],"dc:language.iso":["en"],"dc:publisher.department":["Postgraduate School of Studies in Technological Management"],"dc:publisher.institution":["University of Bradford"],"dc:rights":["<a rel=\"license\" href=\"http://creativecommons.org/licenses/by-nc-nd/3.0/\"><img alt=\"Creative Commons License\" style=\"border-width:0\" src=\"http://i.creativecommons.org/l/by-nc-nd/3.0/88x31.png\" /></a><br />The University of Bradford theses are licenced under a <a rel=\"license\" href=\"http://creativecommons.org/licenses/by-nc-nd/3.0/\">Creative Commons Licence</a>."],"dc:subject":["Construction contracts","Civil engineering projects","Building projects","Case studies","Project management","Decision making"],"dc:title":["Control of construction contracts. Analysis of systems for the control of progress, quality and cost of construction to the client, based upon six cases in building or civil engineering in the UK."],"dc:type":["Thesis"],"dc:type.qualificationlevel":["doctoral"],"dc:type.qualificationname":["PhD"]},"updated_at":"2026-07-24T01:14:20Z"}