An Analysis of Log Truck Turn Times at Harvest Sites and Mill Facilities

Abstract

dc:description.abstract

The raw forest products transportation sector is inherently unique when compared to other transportation industries. The loggers and contractors who transport raw forest products are at a competitive disadvantage. Older equipment is also commonly used by the raw forest products transportation industry in harsh working environments. The average log truck age is 9.7 years while all trucks average only 3.9 years. Nineteen percent of log trucks are 15 years old or older while only 5.9% of all trucks are older than 8 years. Log trucks are regulated by both the Federal Motor Carrier Safety Administration and the state that the truck operates in, thus making interstate transportation more difficult. In addition to these challenges, there is a lack of information concerning efficiency and productivity improvement opportunities related to transporting forest products. This study evaluated truck turn times at both the harvesting site and mill facilities in order to identify important trucking productivity factors and efficiency improvement opportunities. Regression equations were created to estimate truck turn times at harvesting sites and mill facilities. Gross level studies found that 1268 truck turns at the tract scale averaged 1.40 hours while 576 truck turns at the mill scale averaged 0.56 hours. Elemental time studies at four harvesting locations found that log trucks were idle 32% of the time. Trucks spent 29% of time being loaded and 26% of the time waiting. Elemental time studies at mill facilities found that trucks were idle 27% of the time. Trucks spent the greatest amount of time unloading while unbinding was the second greatest contributor to turn times. Reductions in loading and waiting times can have significant effects on the overall turn time. Harvesting contractors could benefit from maintaining balanced harvesting crews. Estimates indicate that harvesting contractors could earn an additional profit of $106,500 over a period of five years by purchasing an additional skidder for those crews whose production is limited due to a lack of skidding capacity. It is estimated that if adding an additional trailer to harvesting crews would allow an additional 2 loads to be transported to the mill each day, harvesting crews could earn an additional $22,100 per year of profit. Road construction can also affect harvesting contractors profits. By minimizing road construction through the use of easements and improved pre-harvest planning, harvesting contractors could reduce road construction costs by as much as $14,000 per tract. With tools available to estimate truck turn around times, harvesting contractors, fleet managers, and truck drivers will be able to make more informed decisions regarding fleet management. This will enable those owning and operating trucks to operate in more efficient and profitable manners. The models created during this study will allow managers to estimate tract and mill turn times so as to better allocate trucking resources.

Degree

thesis:*
Name thesis:degree_name
Master of Science
Level thesis:degree_level
masters
Discipline thesis:degree_discipline
Forestry
Department dc:contributor.department
Forestry
Grantor dc:publisher
Virginia Tech
Year dc:date.issued
2010

Author and committee

dc:creator, dc:contributor.*
Author dc:creator
  • Dowling, Tripp N.
Chair dc:contributor.committeechair
  • Bolding, M. Chad
Committee members dc:contributor.committeemember
  • Aust, W. Michael
  • Fox, Thomas R.

Subjects

dc:subject × 2

Rights

dc:rights
Statement dc:rights
  • In Copyright

Identifiers

dc:identifier.*
Dc Identifier Other
etd-05032010-114017
OAI identifier oai:identifier
oai:vtechworks.lib.vt.edu:10919/32156

Chain of custody

source
Harvested from
Virginia Tech
Base URL
vtechworks.lib.vt.edu/oai/request
Last updated
2026-07-22
Source record
OAI-PMH GetRecord
citation

Dowling, Tripp N.. An Analysis of Log Truck Turn Times at Harvest Sites and Mill Facilities. masters thesis, Virginia Tech, 2010. http://hdl.handle.net/10919/32156